Do you need a permit for a detached garage in Phoenix, AZ?

It depends on size and placement.

Building permit: A garage exceeds Phoenix's 200 sq ft accessory exemption.

Floodplain development permit: If the lot is in a FEMA special flood hazard area, all development there needs a permit.

Rules last checked by a person on October 19, 2026. Guidance only; confirm with Phoenix before you build.

Check your exact lot

Setbacks depend on your zoning district, and a flood zone can change the permit answer. Enter your address to see both.

What are you building?

Permits a detached garage can need in Phoenix

PermitWhen it applies
Building permitA garage exceeds Phoenix's 200 sq ft accessory exemption.
Floodplain development permitIf the lot is in a FEMA special flood hazard area, all development there needs a permit.
Electrical permitWiring needs its own permit.Confidence: medium

Local details

  • Call 811 at least a few days before you dig footings or post holes. Utility locating is free.
  • HOA covenants and deed restrictions can be stricter than city rules. Check yours before you build.

How to apply

Questions people ask

When does a detached garage need a building permit in Phoenix?
A garage exceeds Phoenix's 200 sq ft accessory exemption. Only one-story detached accessory structures up to 200 sq ft are exempt.
Where do I apply for a detached garage permit in Phoenix?
Apply through Phoenix SHAPE PHX permits, or call (602) 262-7811.

Sources

  1. Phoenix Building Construction Code 2024, Chapter 1 amendments (Sec. 105.2, effective 8/1/2025). Checked 2026-10-20.
    One-story detached accessory structures used as tool and storage sheds, playhouses, non-cantilevered shade structures... floor area is not greater than... 200 square feet, except for unaltered Intermodal Shipping Containers not greater than 320 square feet.…
  2. 44 CFR 59.1, definition of development (NFIP). Checked 2026-10-19.
    Development means any man-made change to improved or unimproved real estate, including but not limited to buildings or other structures...
  3. 44 CFR 60.3, floodplain management criteria. Checked 2026-10-19.
    Require permits for all proposed construction or other development in the community...
  4. 2024 IRC R105.2, Work exempt from permit (text published by the City of Benson, AZ). Checked 2026-10-19.
    One-story detached accessory structures, provided that the floor area does not exceed 200 square feet. Fences not over 7 feet high. Decks not exceeding 200 square feet in area, that are not more than 30 inches above grade at any point, are not attached to a…